Updates and Timeline

Stay informed on the construction progress of the new academic building. A tentative timeline and progress updates are posted below.

Updates

Feb 14 - March 30

  • Start structural steel erection

March 15

  • Evaluating the possible addition of photovoltaic solar panels to offset electrical usage in the building

  • Evaluating the site for the possibility of using wind renewable energy

April 8

  • Concrete slabs on third floor to be poured the week of April 12

September 17

  • Footings and foundations on the lecture hall are ongoing and about 50% complete

  • Masonry will start next week with the block backup on the lecture halls

  • First floor of the building is being roughed in with studs and overhead mechanicals work is about 40% complete

  • Second floor is approximately 85% roughed in with stud framing, overhead and in wall MEP

  • Third floor is approximately 95% roughed in

  • Third floor blocking and final roughs will be going on next week

  • Starting drywall on the third floor is anticipated for the week of September 27

  • Fourth floor is being spray fireproofed

  • Mechanicals and framers starting the week of September 27 on the fourth floor

  • North half of the roof is done

  • Working on the penthouses 

  • Windows are about 25% complete

  • Brick veneer is approximately 40% complete with about 115,000 bricks set

 

Tentative Timeline