Updates and Timeline
Stay informed on the construction progress of the new academic building. A tentative timeline and progress updates are posted below.
Updates
Feb 14 - March 30
-
Start structural steel erection
March 15
-
Evaluating the possible addition of photovoltaic solar panels to offset electrical usage in the building
-
Evaluating the site for the possibility of using wind renewable energy
April 8
-
Concrete slabs on third floor to be poured the week of April 12
September 17
-
Footings and foundations on the lecture hall are ongoing and about 50% complete
-
Masonry will start next week with the block backup on the lecture halls
-
First floor of the building is being roughed in with studs and overhead mechanicals work is about 40% complete
-
Second floor is approximately 85% roughed in with stud framing, overhead and in wall MEP
-
Third floor is approximately 95% roughed in
-
Third floor blocking and final roughs will be going on next week
-
Starting drywall on the third floor is anticipated for the week of September 27
-
Fourth floor is being spray fireproofed
-
Mechanicals and framers starting the week of September 27 on the fourth floor
-
North half of the roof is done
-
Working on the penthouses
-
Windows are about 25% complete
-
Brick veneer is approximately 40% complete with about 115,000 bricks set
Tentative Timeline
| Date | Milestone |
|
|---|---|---|
|
Dec 14, 2009 |
|
Construction Start |
|
Dec 2009 |
|
Start Footing Excavation Classroom Building (N) |
|
Feb 2010 |
|
Frame/pour shear walls and complete footings |
|
Mar 2010 |
|
Continue with shear walls and start structural steel erection |
|
Apr 2010 |
|
Start pouring floors as framing is completed |
|
May 2010 |
|
Start work on courtyard |
|
Jun 2010 |
|
Start brick installation; install air handling units in mechanical room |
|
Jul 2010 |
|
Excavate footings for lecture hall building; start window install |
|
Aug 2010 |
|
Start stud wall framing on 4th floor |
|
Sept 2010 |
|
Complete roof on lecture hall building |
|
Oct/Nov 2010 |
|
Continue with wall framing and electrical rough-ins |
|
Dec 2010 |
|
Start interior painting; install laboratory casework on 4th floor; start ceiling install |
|
Jan 2011 |
|
Install flooring on 4th floor; continue with ceiling install |
|
Feb/Mar 2011 |
|
Continue with doors, hardware, ceilings, flooring |
|
April 2011 |
|
Finish site work; install landscaping |
|
May 2011 |
|
Parking lot work |