The new residence hall project will begin construction in 2010 and provide campus with a 340 bed, five-story residence hall. The new facility will be located at the intersection of Algoma Boulevard and Elmwood Avenue, on the site of the current Breese, Nelson and Clemans residence halls. The new facility will be the first suite-style residence hall on campus.
View the renderings of the new residence hall.
Tentative Project Timeline
| Date | Milestone |
|
|---|---|---|
|
Dec 16, 2009 - Jan 12, 2010 |
|
New Building/Site - Review 35% Drawing/Specifications |
|
Dec 29, 2009 - Feb 1, 2010 |
|
Deconstruction - Review 100% Drawing/Specifications |
|
Feb 4 & 5, 2010 |
|
Board of Regents Approval |
|
Feb 19, 2010 |
|
State Building Commission Approval |
|
Apr 1, 2010 |
|
Deconstruction Bids Due |
|
Jun 29, 2010 |
|
Deconstruction Begins - Review 100% |
|
Jul 19, 2010 - Aug 19, 2010 |
|
Drawings/Specifications |
|
Aug 31, 2010 |
|
Deconstruction Complete |
|
Oct 8, 2010 |
|
New Building/Site - Bids Due |
|
Nov 5, 2010 |
|
Construction Begins |
|
May 18, 2012 |
|
Construction Complete |
|
Fall 2012 |
|
Move In |